- 11 April 2022. Issue notice returnable on 8th August, 2022. Meanwhile, there shall be a stay on the impugned order directing payment of compensation, subject to the appellant depositing Rupees One Crore within one month from today with Central Pollution Control Board. This deposit would abide by subsequents orders in this appeal.
- 29 April 2022. List on 06.05.2022. (ARUSHI SUNEJA) (DIPTI KHURANA) SENIOR PERSONAL ASSISTANT
- 6 May 2022. We clarify that in view of the interim order passed by us, it would not be just and proper for the respondent to initiate criminal proceedings against the appellant. However, the appellant must comply with all the requirements and directions issued by the authorities. In case of non-compliance and failure on part of th
- 8 August 2022. Mr. Pradeep Misra, who entered appearance on behalf of respondent No.4 states that the details/report asked for in terms of the order dated 11.04.2022 require inputs and details from the District Magistrate and the District Ground Water Management Council. The State of Uttar Pradesh is the respondent No.5 before this C
- 16 January 2023. In view of the letter circulated by the learned counsel for respondent no.5-State of Uttar Pradesh seeking adjournment, re-list in the month of April 2023. Counter affidavit/reply will be filed by respondent no.5 on or before 15.03.2023.
- 5 April 2023. In view of the request made, the respondent no. 5 - State of Uttar Pradesh is granted four weeks' time from today to file counter affidavit/reply. Rejoinder, if any, within four weeks after service of the counter affidavit/reply. Re-list in the month CA No. 2653/2022 of September 2023. Steps for effecting service on th
- 27 September 2023. Respondent no. 1 has not been served. As per the office report, he is not available at the address. As per the learned counsel for the appellant, respondent no. 1 is not traceable. Appellant to take steps in accordance with law.
- 27 February 2024. In spite of several attempts, respondent no. 1 has not been served. I.A. no. 36351/2024 for substituted service is allowed in terms of the prayer clause. CA No. 2653/2022 The Central Ground Water Authority 1 is directed to file an affidavit, specifically dealing with the figures and the data furnished by the Uttar Prad
- 26 July 2024. Our attention is drawn to the short affidavit filed by respondent No. 5 and the figures mentioned therein. We would like the State Government to examine the said figures and inform the Court about the steps taken to recharge/recoup the groundwater levels in District Amroha, Uttar Pradesh and other parts of the State. W
- 5 December 2024. There is non-compliance with the order dated 26.07.2024. In view of the long delay and as a further adjournment is now CA No. 2653/2022 sought for, costs of 10,000/- (Rupees ten thousand only) will be₹ paid by respondent No. 5, State of Uttar Pradesh, who must comply with the earlier order dated 26.07.2024 and file the
- 4 August 2026. List on 01.12.2026.
- Counsel named on these orders, not a complete vakalatnama, include the advocates listed below.
Advocates — Appellants: Mr. Pinaki Mishra, Mr. Ashish Prasad, Mr. Abhishek Shivpuri, Mr. Pruthvi Dhinoja, Mr. Mahfooz Ahsan Nazki, Mr. Gopal Shankar Narayan, Ms. Aditi Gupta, Mr. Mahfooz A. Nazki, Mr. Karan Dev Chopra, Mr. Neeraj Malik, Ms. Mumtaz Bhalla, Mr. Lakshya Kampani Advocates — Respondents: Mr. Chirag Joshi, Mr. Ghanshyam Joshi, Mr. Pradeep Misra, Mr. Daleep Dhyani, Mr. Suraj Singh, Mr. Avneesh Arputham, Mr. Ankit Sharma, Mr. Bhuwan Chandra, Mr. Manoj Kumar Sharma, Ms. Anuradha Arputham, Mr. Rana Mukherjee, Mr. Rajeev Kumar Dubey