- 6 May 2011. Issue show-cause notice as to why these No stay. Tag these appeals with Civil Appeal Nos.1090-1099 of 2011.
- 12 August 2011. Exemption allowed. Permission to bring additional facts and documents on record is granted.
- 20 September 2011. Await return of notice of the unserved respondents. List the matter on 8.11.2011.
- 8 November 2011. In C.A.No.2859/2011 Ld. counsel for the appellant seeks dasti notice against both the respondents. Granted. Await return of notice of both the unserved respondents in each of the above cases. Served respondents are granted four weeks time for filing counter affidavit. List the matters on 9.12.2011.
- 9 December 2011. File is not received. List the matter on 13.01.2012.
- 13 January 2012. Service is complete only in C.A.No.3171/2011. In all other cases service is incomplete. Await unserved. List the matters on 27.2.2012.
- 27 February 2012. File is not received. List the matter on 10.04.2012.
- 20 March 2012. File not received. List the matter on 20.4.2012.
- 10 April 2012. Await return of notice of all unserved respondents. List the matter on 2.07.2012.
- 2 July 2012. Await return of notice of the unserved respondents. List the matter on 3.08.2012.
- 3 August 2012. It is seen that in few of the cases service is incomplete. However, counsel for the parties submit that these are appeals inter se and cross appeals and some of the parties who are unserved are either the served respondents or the appellants in some of the cases. Office to verify that any of the unserved respondent is
- 19 September 2012. Files not received. Hence, adjourned. List the matters on 8.10.2012.
- 8 October 2012. The office report indicates that the unserved respondents have been served in the connected matter and thereby service is deemed as complete on all the unserved respondents. Await records. List the matters on 4.12.2012.
- 4 December 2012. File not received. List on 21.1.2013.
- 21 January 2013. Files is not received. Hence, adjourned. List the matters on 12.2.2013.
- 12 February 2013. Await records. List the matter on 4.04.2013.
- 4 April 2013. Service is complete in Civil Appeal No.2859/11 and Civil Appeal No.3453/11. Ld.counsel for the respective appellants are directed to take fresh steps against the unserved respondents. List the matter on 8.07.2013.
- 8 August 2013. Service is not complete in Civil Appeal Nos. 2859 and 3453/2011. ..2/ ITEM NO.66 The learned counsel for the appellant is granted four weeks' time as last chance for takings steps against the unserved respondents.
- 25 October 2013. Learned counsel for the appellant has not taken steps in spite of last chance granted. However, I am inclined to grant four more weeks time subject to the condition that he takes steps and deposits a sum of Rs. 500/- in the ..2/ Item No. 27 Supreme Court Legal Services Committee as composite cost within four weeks. If
- 20 February 2014. The appellant has neither taken the steps nor paid the cost as ordered by order dated 25.10.2013. Hence, list the matter before Hon'ble Judge-in-Chamber with appropriate office report on default. Await orders.
- 18 August 2015. Learned counsel for the appellant submits that on 14th August, 2015 he has deposited the cost of Rs.500/ and sought permission to serve the unserved respondent No.1 which is the appellant in the connected C.A. Nos. 1090-1099 of 2011.
- 12 October 2020. Ld. counsel for the appellant has not furnished the complete details/particulars of Bank officials viz., name, designation, contact numbers, e-mail ID, compendium of scanned signature of Bank officials , authority letter, self -attested copy of ID proof of Bank Officials. Ld. Counsel for the petitioner seeks time to fu
- 20 November 2020. Ld. counsel for the appellant to furnish the ID proof (Aadhar Card, PAN Card, etc.) of Bank officials within one week so that the authenticity could be verified by the Registry. List again on 9.12.2020.
- 9 December 2020. Mr.R. Ramesh Kumar, Manager, State Bank of India, Commercial Branch, Chennai and Mrs. J.M. Kurinjimalar, Deputy Manager, State Bank of India, International Banking Divisio n, Commercial Branch, Chennai have been authorised to verify the extended Bank Guarantee No.0734720BG0000017 dated 10.02.2020 for Rs.75,00,00,000/-
- 4 March 2021. As per office report, the documents filed to verify the extension of Bank Guarantee are found to be defective. However, Ld. counsel for the appellant has pointed out that the defects as communicated by the Registry have already been removed on 18.2.2021. Registry to verify and proceed further.
- 26 July 2021. I am told that this matter has been placed before this Court for renewal of the Bank Guarantee. I am of the opinion that verification of the documents filed by the parties is the job of the Branch on Administrative side. I believe that has already been done. If the documents so filed are in order as per the Supreme Cou
- 12 August 2022. Learned counsel for the appellant prays for and is granted time upto Ist week of September, 2022 to do the needful. Let needful be done upto the time as prayed for.
- 26 September 2022. The office report indicates that the learned counsel appearing for the appellant has neither filed the relevant documents of the authorized bank officials nor has informed the Registry about the fresh date to produce the officials along with the necessary documents for verification and acceptance of the said bank guara
- 17 October 2022. This matter has been placed before this Court for consideration of renewal of the Bank Guarantee filed by the ld. counsel for the appellant in terms of order dt.04.02.2011 passed by the Hon'ble Court.
- 17 May 2023. Ld. counsel for the appellant has e-filed Extended Bank contd…. Guarantee valid upto 9.2.2024, but has not filed Original Extended Bank Guarantee. Two weeks' time is granted for doing the needful.
- The record also contains 12 further orders. Each file is listed on the Orders tab.
- Counsel named on these orders, not a complete vakalatnama, include the advocates listed below.
Advocates — Appellants: Mr. R.S. Pandiyaraj, Mr. S.P. Parthasarathy, Mr. M. Parthiban, Mr. S. Gowthaman, Mr. Shyam Divan, Mr. K.V. Viswanathan, Mr. Anil Kaushik, Ms. Arunima Dwivedi, Mr. Shiv Prakash Pandey, Mr. N.L. Rajah, Mr. Nikhil Nayyar, Mr. T.V.S. Raghavendra Sreyas Advocates — Respondents: Mr. S. Gowthaman, Mr. P. Parmeswaran, Mr. Danish Zubair Khan, Mr. Shiv Prakash Pandey, Ms. Arunima Dwivedi, Mr. G.S. Chauhan, Mr. Nikhil Nayyar, Mr. Shaillendera Kishore Singh, Mr. Krishna Dev, Mr. Danish Zuber Khan, Mr. Gopal Singh Chauhan, Mr. Shailendera Kishore Singh