- 9 January 2026. 1. Ms. Swapna Seshadri, the learned counsel appearing for the appellant – Power Grid Corporation of India Limited submitted that the appellant has preferred a Review Petition before the Appellate Tribunal. She prays that let this appeal be adjourned till the time the Review Petition is decided. 2. Post this appeal in t
- 13 March 2026. In view of letter circulated by the learned counsel for the appellant seeking six weeks adjournment on the ground that the appellant has filed Review Petition before the Appellate Tribunal and he would want to await the result of the review petition, the matter is adjourned for six weeks.
- 14 May 2026. 1. Admit. 2. Issue notice as to interim relief, returnable after four weeks.
- 20 July 2026. Tag with Civil Appeal Nos. 14780-14781/2025.
- 24 July 2026. List this I.A. next week.
- 31 July 2026. List the appeals along with I.A. No.143676/2026 and connected (HARPREET KAUR) (POOJA SHARMA)
- 6 August 2026. List on Wednesday, the 12.08.2026 along with all the interlocutory applications.
- 12 August 2026. 1. The Central Electricity Regulatory Commission shall not proceed further till we decide the main appeal pending before us. 2. List the appeals on 19.08.2026 for final hearing as item no.101.
- 19 August 2026. 1. Post these matters on 16-9-2026. 2. The matters shall retain its position.
- Counsel named on these orders, not a complete vakalatnama, include the advocates listed below.
Advocates — Appellants: Ms. Swapna Seshadri, Mr. Pramod Dayal, Mr. Nikunj Dayal, Mr. Utkarsh Singh, Ms. Rupinder Kaur, Mr. Ramji Srinivasan, Ms. Namrata Saraogi, Mr. Tushar Mehta, Ms. Shefali Munde, Mr. Aryansh Tripathi, Ms. Radhika Gaur Advocates — Respondents: Mr. Mahesh Agarwal, Mr. Rishi Agrawala, Mr. Arshit Anand, Ms. Vidisha Swarup, Ms. Siddhi Gupta, Mr. E. C. Agrawala, Mr. Matrugupta Mishra, Mr. Nipun Dave, Mr. V. Giri, Ms. Vanshika Saraf, Mr. Sajan Poovayya, Ms. Raksha Agarwal