- 18 July 2017. Ld.counsel for the appellant shall file the spare copies for issuance of NLPA to the respondents within two weeks. FDR may be renewed for a further period of six months.
- 30 August 2017. Registry to process the matter as per Rules.
- 7 December 2017. Respondent Nos. 1 to 3 are duly represented in both the matters. Parties have not filed the Statements of Case and the stipulated time has expired.
- 15 December 2017. F.D.R. be renewed for a further period of 91 days from the due date of its maturity.
- 16 January 2018. FDR may be renewed for a further period of six months from the due date of its maturity.
- 14 March 2018. FDR is renewed for a further period of ninety one days from the due date of its maturity.
- 2 July 2018. FDR is renewed for a further period of 91 days from the due date of its maturity.
- 12 July 2018. FDR is renewed for a further period of six months from the due date of its maturity.
- 10 September 2018. FDR is renewed for a further period of 91 days from the due date of its maturity.
- 26 November 2018. List the matter for final disposal on a non-miscellaneous day in the 1st week of February, 2019.
- 10 December 2018. F.D.R. be renewed for a further period of 91 days from the due date of its maturity.
- 21 January 2019. FDR be renewed for a further period of six months from the date of its maturity.
- 1 April 2019. F.D.R. be renewed for a further period of 91 days from the date of its maturity.
- 28 June 2019. FDR may be renewed in terms of the Guidelines dated 29.5.2006 of the then Hon'ble The Chief Justice of India in a nationalized bank to earn maximum interest.
- 4 July 2019. F.D.R. be renewed for a further period of 91 days from the due date of its maturity.
- 23 July 2019. FDR is renewed for a further period of six months from the due date of its maturity.
- 5 August 2019. This is an application for early hearing. Having heard learned counsel for the applicant, we are not inclined to allow the prayer for early hearing at CA 3097-98/17 this stage. The interlocutory application for early hearing is dismissed.
- 30 September 2019. FDR is renewed for a further period of 91 days from the due date of its maturity.
- 18 December 2019. F.D.R. be renewed for a further period of 91 days from the due date of its maturity.
- 30 January 2020. FDR be renewed for the period of six months from the due date of its maturity.
- 30 July 2020. FDR be renewed for a further period of six months from the due date of its maturity.
- 6 October 2020. F.D.R. be renewed for a further period of six months from the due date of its maturity.
- 27 January 2021. FDR be renewed for a further period of six months from the due date of its maturity.
- 9 April 2021. FDR be renewed for a period of one year from the date of its maturity.
- 19 July 2021. FDR be renewed for a further period of six months from the due date of its maturity.
- 24 January 2022. FDR be renewed for a further period of six months from the due date of its maturity i.e., 5.2.2022.
- 29 March 2022. FDR be renewed for a further period of one year from the due date of its maturity i.e. 21.4.2022.
- 19 July 2022. In view of higher interest and for the benefit of party, F.D.R. may be renewed for a further period of one year.
- 6 April 2023. F.D.R. be renewed for a further period of one year from the due date of its maturity. Registry to proceed further, as per rules.
- 26 July 2023. F.D.R. may be renewed for a further period of one year.
- The record also contains 9 further orders. Each file is listed on the Orders tab.
- Counsel named on these orders, not a complete vakalatnama, include the advocates listed below.
Advocates — Appellants: Mr. Abhishek, Mr. Anupam Lal Das, Mr. Anirudh Singh, Mr. Krishanu Barua, Mr. Gaurav Agrawal, Mr. D.Malhotra, Mr. Ashish Bhagat, Mr. Aman Lekhi, Mr. R. Balasubramanyan, Mr. S.S. Ray, Mr. Abhishek Kumar, Mr. B.V. Balram Das Advocates — Respondents: Mr. Anupam Singh, Mr. Akshay Girish Ringe, Mr. Gautam Jha, Mr. Ananya Ghosh, Mr. Victor Das, Mr Siddarth Joshi, Mr Siddharth Joshi, Ms Megha Mukerjee, Mr. Abhishek, Mr. Siddhartha Jha, Mr. Sarad Kumar Singhania, Mr. K.L.Janjani