- 22 March 2024. Delay condoned. Issue notice and tag with Civil Appeal No.8430/2022 titled “Municipal Corporation Ghaziabad v. Central Pollution Control Board”.
- 26 July 2024. Municipal Corporation, Ghaziabad 1, has deposited 2 crores.₹ Ghaziabad Development Authority 2, it is stated, has deposited 5 ₹ crores in the escrow account which was opened yesterday, i.e., 25.07.2024. Further payment of 15 crores will be made within a₹ period of four weeks from today. Learned counsel for the Uttar Pr
- 18 October 2024. It is stated that the Ghaziabad Development Authority 1 has deposited 15 crores, in terms of order dated 26.07.2024.₹ There is non-compliance by respondent no. 2, Uttar Pradesh Pollution Control Board, with the order dated 09.10.2023 read with the order dated 26.07.2024, as a status report has not been filed. Responden
- 10 December 2024. Four weeks time, is granted to respondent Nos. 1 and 2 to file counter affidavit. As per postal tracking report notice issued to respondent No.3 has been received back with postal remarks “Unclaimed”. Service is deemed complete on the said respondent in view of order passed in K. Bhaskaran Vs. Sankaran Vaidhyan Balan &
- Counsel named on these orders, not a complete vakalatnama, include the advocates listed below.
Advocates — Appellants: Mr. Devashish Bharuka, Ms. Tulika Mukherjee, Ms. Sarvshree, Ms. Ekta Bharati, Mr. Beenu Sharma, Mr. Venkat Narayan, Mr. Malak Manish Bhatt, Ms. Neeha Nagpal, Ms. Sukanya Joshi, Mr. Harshit Rastogi, Mr. Harshit Gupta Advocates — Respondents: Mr. Saurabh Mishra, Mr. Abhinav Pandey, Mr. Shrimay Mishra, Mr. Rakesh Chander, Ms. Anuradha Mishra, Mr. Arvind Kumar, Mr. James Bedi, Mr. K.S. Captain, Mr. Ankit Kumar, Mr. Ajay Agarwal, Mr. Rajeev Kumar Dubey, Mr. Ashiwan Mishra